Bolton Incinerator Plant Rewire

Due to extreme environmental conditions, the wiring and associated components of the plant had degraded to the point where a complete rewire of the process was necessary. This included the replacement of a number of outstations, and the replacement of the MCC.

Also due to the age of the installation, it was necessary to review and replace the safety system, which we replaced with a Pilz programmable unit.

This project was undertaken in 10 weeks with a 4-week shutdown.